Physical & Financial Progress of Completed/ Ongoing sub projects under RUIDP- Phase II
    Month:   Amount in lacs        
  SN Package ID Contract  Price  Expenditure upto July-19 St date of start Actual date of completion Date of hand over Status of use
  A Alwar            
1 1 RUSDIP/TR-01/ALW-JHL/WS-01 Lot-1 (Alwar) 348.96 309.09 23-06-2008 24-02-2010 17-08-2010 Under use
2 2 RUSDIP/ TR-01/ALW/WS/ 02 1794.71 1714.80 09-09-2008 12-06-2012 Handed over Under use
3 3 RUSDIP/TR-01/ALW/WS/03 513.08 329.94 06-09-2010 31-03-2017 31-03-2017 Under use
4 4 RUSDIP/    TR-01/ ALW/WW/01 Lot-2  728.00 696.64 15-12-2008 06-09-2010 03.11.2010 Under use
5 5 RUSDIP/ TR-01/ALW/WW /02 Lot-1 1903.80 1674.14 10-07-2009 20-07-2012 07.03.2013 Under use
6 6 RUSDIP/TR-01/ALW/WW/02 Lot-2 992.54 1172.74 21-08-2009 18-12-2012 07.03.2013 Under use
7 7 RUSDIP/TR-01/ALW/WW/03 1719.96 1621.85 25-03-2011 27-02-2017 06.06.2018 Under use
8 8 RUSDIP/TR-01/ALW/WW/05 2092 1862.86 15-05-2013 19-06-2017 06.06.2018 Under use
9 9 RUSDIP/TR-02/ALW/WW/06 3681 2701.50 22-08-2014 30-01-2018 06.06.2018 Under use
10 10 RUSDIP/TR-01/ALW/BR/01 1557.59 2161.96 13-07-2009 30-04-2012 16.12.2016 Under use
11 11 RUSDIP/TR-02/ALW/BR/02 2225.72 2217.19 12-09-2012 27-01-2015 30.07.2015 Under use
12 12 RUSDIP/TR-01/ALW/SW/05 190.7 210.96 24-08-2009 17-10-2012 12.12.2012 Under use
13 13 RUSDIP/TR-03/ALW/FR/01 272.51 239.66 18-03-2011 15-09-2012 12.12.2012 Under use
    Total ##### 16913.3        
  B Bharatpur            
14 1 RUSDIP/TR-02/BPR/WS/05 2000 1678.81 09-04-2011 10-02-2016 25.10.2016 Under use
15 2 RUSDIP/TR-02/BPR/WS-03 2094.03 2250.07 25-03-2010 30-05-2014 02.09.2014 Under use
16 3 RUSDIP/ TR-02/ BPR/DR/02 857.58 808.79 28-11-2009 30-11-2012 07.03.2014 Under use
17 4 RUSDIP/TR-03/BPR/FR/01 125.78 106.54 01-04-2011 30-11-2012 24.04.2013 Under use
18 5 RUSDIP/TR-02/BPR/ST-01 3446.35 4146.68 19-07-2012 10-01-2016 22.01.2016 Under use
19 6 RUSDIP/ TR-02/ BPR/BR/02 1375.75 1510.64 27-05-2015 31-05-2017 Under process Under use
20 7 RUSDIP/TR-03/BPR/WW-01/Lot-01 4631.22 4108.04 24-02-2011 31-07-2018 Under process Under use
21 8 RUSDIP/TR-03/BPR/WW-02 1084.06 801.83 05-04-2018 30-06-2017 Under process Under use
    Total 16472 16305.6        
  C Dholpur            
22 1 RUSDIP/TR-03/DLP/HS/01 44.08 30.65 04-04-2011 18-01-2012 04.09.2013 Under use
23 2 RUSDIP/TR-03/DLP/ST/01 530.72 535.53 18-08-2011 28-06-2013 10.03.2015 Under use
24 3 RUSDIP/TR-03/DLP/ST/02 1347.00 1443.07 26-06-2012 26-09-2014 05.10.2015 Under use
25 4 RUSDIP/TR-03/DLP/ST/03 1306.22 1330.73 26-07-2012 15-05-2016 30.06.2017 Under use
26 5 RUSDIP/TR-02/DLP/WW/05 724.58 749.05 04-11-2010 31-05-2016 26.09.2016 Under use
27 6 RUSDIP/TR-02/DLP/WW/04 2496.76 3854.22 22-07-2010 31-01-2018 04.06.2018 Under use
28 7 RUSDIP/TR-02/DLP/WW/08 2058.95 1858.28 23-05-2013 30-11-2017 04.06.2018 Under use
29 8 RUSDIP/TR-02/DLP/WW/11 2266.04 1899.58 28-07-2014 13-12-2018 04.06.2018 Under use
30 9 RUSDIP/TR-02/DLP/WS/03 2354.12 3150.1 22-03-2010 15-09-2016 08.06.2016 Under use
    Total ##### 14851.2 ####### 381588.00    
  D Karauli            
    Completed works            
31 1 RUSDIP/TR-03/KRL/HS/01 126.43 133.47 25-03-2011 23-05-2012 23.05.2012 Under use
32 2 RUSDIP/TR-02/KRL/WS/01 2864.35 3120.55 17-07-2009 31-12-2014 02.02.2018 Under use
33 3 RUSDIP/TR-03/KRL/WW/05 2533.68 2099.3 13-05-2013 30-06-2017 Under process Under use
34 4 RUSDIP/TR-03/KRL/WW/06 716 578.73 11-08-2017 10-09-2018 Under process Under use
    Total ##### 6635.54        
  E Sawai Madhopur            
35 1 RUSDIP/TR-02/SMD/BR/01 1868.03 2318.95 20-08-2009 31-03-2013 20.05.2013 Under use
36 2 RUSDIP/TR-03/SMD/DR/01 328.34 318.41 22-12-2010 21-06-2012 Handed over Under use
37 3 RUSDIP/TR-03/SMD/HS/01 18.73 17.25 31-03-2011 11-04-2012  Hand over not required Under use
38 4 RUSDIP/TR-03/SMD/BR/03 720.19 679.24 27-04-2012 30-09-2013 Handed over Under use
39 5 RUSDIP/ TR-02/ SMD/WW/02 3175.1 3781.24 04-11-2009 05-03-2014 18.02.2016 Under use
40 6 RUSDIP/TR-02/ SMD/WS/02 2674.67 2553.54 18-01-2010 30-06-2016 30.06.2016 Under use
    Total 8785.1 9668.6        
  F Jaisalmer            
41 1 RUSDIP/TR-01/ JSL/DR-01 534.38 427.62 08-07-2008 30-09-2010 Handed over Under use
42 2 RUSDIP/ TR-01/JSL/WS /01 6968.14 7791.45 08-07-2009 12-12-2012 22.03.2013 Under use
43 3 RUSDIP/TR-01/JSL/WW-09 1539.36 1195.17 15-03-2013 29-04-2016 Handed over Under use
44 4 RUSDIP/TR-03/JSL/WW-06 720.97 294.56 17-01-2013 31-05-2017 Handed over Under use
45 5 RUSDIP/JSL/WS-03 114.44 65.76 07-02-2018 06-05-2018 Handed over Under use
46 6 RUSDIP/JSL/WW-10 839.08 873.35 07-02-2018 14-08-2018 Not handed over Under use
47 7 RUSDIP/TR-01/JSL/SW-07 89.55 72.60 24-08-2009   Work Withdraw  
    Total ##### 13524.0        
  G Sikar            
48 1 RUSDIP/TR-02/SKR/WS-03  978.85 1004.13 25-10-2011 30-06-2014 18.09.2014 Under use
49 2 RUSDIP/TR-02/SKR/ST-04 1136.16 1261.22 14-08-2012 31-08-2014 13.05.2015 Under use
50 3 RUSDIP/TR-02/SKR/DR-01 379.32 467.32 08-07-2009 30-06-2012 29.10.2013 Under use
51 4 RUSDIP/TR-02/SKR/ST-05 2343.100 2581.05 16-11-2012 23-06-2015 08.03.2016 Under use
52 5 RUSDIP/TR-02/SKR/WS-02  1249.950 709.47 30-12-2010 31-07-2015 Handed over Under use
53 6 RUSDIP/TR-02/SKR/ST-02  1126.44 1313.57 22-07-2011 31-10-2015 Handed over Under use
54 7 RUSDIP/TR-02/SKR/WS-04  2305.000 1814.25 10-01-2013 21-11-2017 Handed over Under use
    Total 10034 9665.7        
  H Nagaur            
55 1 RUSDIP/TR-02/NGR/WW/03 1812 1577.5 13-03-2013 07-09-2014 12-10-2018
(EE PIU letter)
Under use
56 2 RUSDIP/TR-02/NGR/WS/01 2918.52 2475.63 20-08-2009 19-05-2015 29-01-2014 Under use
57 3 RUSDIP/TR-03/NGR/WS/02 975 817.58 05-08-2014 28-02-2017 18-04-2017
(EE PIU letter)
Under use
58 4 RUSDIP/TR-02/NGR/WW/02/Lot-2 1105 903.09 08-08-2012 26-02-2018 14-05-2019
(EE PIU letter)
Under use
59 5 RUSDIP/TR-03/NGR/ST/01 1211 1158.97 23-07-2014 23-08-2017 Terminated and balance amount deposited to PWD Under use
60 6 RUSDIP/TR-03/NGR/WW/05 3472 3678.24 31-07-2014 15-09-2018 Under process Under use
    Total 11783 10830        
  I Churu            
61 1 RUSDIP/TR-02/CHU/BR/01 2263.19 3302.57 22-08-2009 21-04-2013 14.09.18 Under use
62 1 RUSDIP/TR-03/CHU/DR-03 1777 1782.73 24-12-2012 30-05-2016 25.07.18 Under use
63 2 RUSDIP/TR-03/CHU/ST-01 1372.17 1337.59 23-07-2014 25-01-2017 13.08.18 Under use
64 3 RUSDIP/TR-03/CHU/DR-04 1817.71 1836.79 28-05-2013 30-06-2017 25.07.18 Under use
65 5 RUSDIP/ TR-03/ CHU/WW-01 3363 4033.37 16-03-2012 31-08-2017 25.07.18 Under used
66 6 RUSDIP/ TR-02/  CHU/ WS/02 1148.07 1140.08 20-05-2010 15-07-2014 Terminated on 15.07.2014  
    Total 14408 15452.4        
  J Barmer            
67 1 RUSDIP/BMR/TR-02/BR-01 1854.52 2342.66 16-04-2011 31-01-2014 22.04.2015 Under use
68 2 RUSDIP/BMR/TR-03/ST-01 723.94 654.71 03-08-2012 04-08-2015 02.11.2013 Under use
69 3 RUSDIP/BMR/TR-02/WS-02 2472.47 2682.86 28-06-2010 26-06-2016 06.05.2015 Under use
70 4 RUSDIP/BMR/TR-02/WW-03/Lot-02 799.99 882.53 19-07-2012
19-09-2017 20.06.2018 Under use
71 5 RUSDIP/BMR/TR-02/WW-03/Lot-01 1902.92 1822.32 03-08-2012 14.01.2019 Under process Under use
    Total 7902.7 8533.9        
  K Jhalawar            
72 1 RUSDIP/TR-01/JHL/WS-02 2901.58 2573.23 05-09-2008 31-05-2016 22.05.2013 Under use
73 2 RUSDIP/TR-03/JHL/HS/01 241.52 244.2 22-07-2011 24-01-2014 27.01.2014 Under use
74 3 RUSDIP/TR-01/JHL/SW-08 86.45 71.32 12-02-2010 31-01-2015 Handed over Under use
75 4 RUSDIP/TR-02/JHL/WW-02  1858 1592.50 03-05-2013 30-04-2017 30.04.2018 Under use
    Total ##### 4481.25        
  L Baran            
76 1 RUSDIP/TR-03/BRN/WS/01 3100.38 3014.61 25-02-2011 02-05-2016 09.07.2015 Under use
77 2 RUSDIP/TR-02/ BRN/BR-02 2421.11 3360.56 20-08-2009 30-11-2013 28.04.2014 Under use
78 3 RUSDIP/TR-03/BRN/SW/01 110.32 110.27 01-11-2011 30-11-2013 25.04.2014 Under use
79 4 RUSDIP/TR-03/BRN/HS/01 90.8 68.98 13-09-2011 16-08-2012 12.04.2013 Under use
80 5 RUSDIP/TR-02/BRN/ST/01 790.39 768.57 23-07-2014 22-11-2015 04.03.2016 Under use
    Total 6513 7323        
  M Rajasmand            
81 1 RUSDIP/TR-03/RSM/SW/01 103.72 98.98 23-11-2011 19-02-2014 29.02.2014 Under use
82 2 RUSDIP/TR-03/RSM/ST/01 1312.22 1266.66 19-07-2012 15-07-2015 Not taken by ULB Under use
83 3 RUSDIP/TR-02/RSM/WS/03 2863.55 2961.93 20-05-2010 15-07-2016 28.07.2016 Under use
84 4 RUSDIP/ TR-02/ RSM/WW/03 1840 1061.35 27-05-2015 10-07-2017 24.07.2018 Under use
    Total 7515.3 6784.7        
  N Bundi            
85 1 RUSDIP/TR-03/BND/HS/01 369.51 178.43 21-07-2011 02-03-2015 27.01.2016 Under use
86 2 RUSDIP/TR-02/ BND/WS/02 2698.23 2463.95 03-11-2009 30-06-2015 25.07.2014 Under use
87 3 RUSDIP/TR-02/BND/ST/04 1928 2552.92 09-08-2012 04-01-2018 06.03.2017 Under use
88 4 RUSDIP/ TR-02/ BND/WW/06 2934 2646.91 24-08-2015 24-08-2017 04.01.2018 Under use
    Total 8211.8 8137.6        
  L Chittorgarh            
89 1 RUSDIP/TR-02/CHT/BR/01 881.00 1065.90 13-07-2009 12-07-2011   Under use
90 2 RUSDIP/TR-03/CHT/FR/01 80.14 57.52 22-07-2011 21-07-2012   Under use
91 3 RUSDIP/TR-03/CHT/WS/01 3344 3876.11 25-03-2011 24-10-2016 05.08.2017 Under use
92 4 RUSDIP/TR-03/CHT/BR-03 240.62 562.40 28-09-2012 29-02-2016 16.12.2016 Under use
93 5 RUSDIP/TR-03/CHT/WW/01/Lot.2 541 449.93 28-04-2011 01-10-2017 07.08.2018 Under use
94 6 RUSDIP/TR-03/CHT/WW/01/Lot.1 3064.01 2524.87 16-11-2011 31-03-2018 Not handed over Under use
    Total ##### 8536.73        
  16 Completed PMU WORKS            
95 1 RUSDIP/TR-01/ALW-JHL-JHP-JSL/SW/01 75.71 75.14 15-12-2008 16-09-2009 07.05.2010 Under use
96 2 RUSDIP/TR-01/ALW-JHL-JHP-JSL/SW/02 37.94 37.64 15-12-2008 14-09-2009 14-09-2009 Under use
97 3 RUSDIP/TR-01/ALW-JHL-JHP-JSL/SW/02 161.82 160.70 15-12-2008 24-05-2010 08-07-2010 Under use
98 4 RUSDIP/TR-01/ALW-JHL-JHP-JSL/SW/02 67.60 65.02 15-12-2008 13-01-2011 13-01-2011 Under use
99 5 RUSDIP/TR-01/ALW-JHL-JHP-JSL/SW/03 86.86 83.34 15-12-2008 14-12-2009 14-12-2009 Under use
100 6 RUSDIP/TR-03/PMU/SW/02 65.24 74.12 28-12-2010 21-01-2012 21-01-2012 Under use
101 7 RUSDIP/TR-03/PMU/SW/04 203.44 213.06 28-12-2010 09-09-2011 09-09-2011 Under use
102 8 RUSDIP/TR-03/PMU/SW/05 312.7 323.30 28-12-2010 12-10-2012 12-10-2012 Under use
103 9 RUSDIP/TR-03/PMU/FR/03 339.86 345.36 09-03-2011 05-09-2012 05-09-2012 Under use
104 10 RUSDIP/TR-03/PMU/FR/04 83.63 93.62 09-03-2011 05-09-2012 05-09-2012 Under use
105 11 RUSDIP/TR-03/PMU/FR/05 302.43 341.23 24-10-2011 05-11-2012 05-11-2012 Under use
106 12 RUSDIP/TR-03/PMU/SW/07 272.72 298.19 24-10-2011 27-02-2013 27-02-2013 Under use
107 13 RUSDIP/TR-03/PMU/SW/06 145.03 147.17 24-10-2011 28-02-2014 28-02-2014 Under use
108 14 RUSDIP/TR-02/PMU/CB/02 381.95 440.79 04-06-2012 11-07-2013 11-07-2013 Under use
109 15 RUSDIP/TR-03/PMU/FR/02 334.2 327.46 22-08-2011 12-08-2014 12-08-2014 Under use
    Total 2871 3026        
    Grand Total 159754 160670        
    Others 16545 16694        
      176299 177363   Percentage